Glendale’s hazardous materials inventory statement, and the site plan the fire code calls for.
Glendale follows the 2024 International Fire Code and publishes its own inventory statement form. The city did not rewrite the code’s hazardous materials chapter, so the drawing requirements are the code’s own. RevealBuilt measures the building and draws them.
What Glendale publishes
- The code in force. Glendale Fire Prevention says the city is using the 2024 International Fire Code with city amendments.
- An inventory form. The Fire Prevention page offers the department’s HMIS spreadsheet, listed as Regulation 5001.
- No local rewrite of Chapter 50. The city’s 2024 fire code amendments do not change the hazardous materials chapter, the management plan section or the inventory statement section.
- Appendix H is adopted. The amendments adopt the code’s appendix of HMMP and HMIS instructions, to be used as an alternate method, an optional consideration or a requirement as the fire code official determines.
- A posted floor plan at the alarm panel. The Fire Prevention Office’s Contractors Guide says an approved simplified floor plan of the areas served by the fire alarm system shall be posted near the annunciator panel, with zone descriptions matching the plan. The guide does not cover hazardous materials.
So in Glendale the model code applies as written: an inventory statement and a management plan are required with a permit application where the fire code official requires them.
The drawings
Glendale’s own pages do not describe a site plan. The code the city adopted does, and so does the state.
The fire code’s site plan. Where a hazardous materials management plan (HMMP) is required, International Fire Code Section 5001.5.1 calls for a facility site plan. Appendix H of the code describes the storage map: a floor plan of each building that holds hazardous materials, on letter-size paper, with north marked and each storage and use area shown, hazardous waste included. It lists:
- Access to each storage and use area
- Emergency equipment
- Where responders meet your liaison
- Evacuation meeting points
- Tanks above and below ground, with their piping
- The hazard classes in each area
- Control areas, Group H areas and exterior storage and use areas
- Emergency exits
The state’s site map. ADEQ states that a site map is mandatory for every facility submitting a Tier II report, showing every way in and out, where substances are stored, and the general layout.
One scan of the building is the base for both drawings.
How RevealBuilt fits
- We scan the building once and draw a measured floor plan and site plan to scale, with north and the drawing date.
- We place what the list calls for that we can see on site: exits, access, emergency equipment, tanks, shut-offs.
- You or your consultant supply the chemical locations, hazard classes and control area boundaries, and we draw them in.
- We do not classify materials, prepare the inventory statement or the management plan, or file anything with Glendale.
A measured site map from one scan of the building is $500 plus $0.05 per square foot scanned, with no travel charge anywhere in Glendale. Map update when storage moves $250. A drawing set made to a fuller HMMP list is quoted by the site before we schedule. For Arizona facilities we also prepare the Tier II report: $995 per facility, up to 30 chemicals.
Which fire code does Glendale use?
Glendale Fire Prevention states that the city is currently using the 2024 International Fire Code with city amendments.
Does Glendale have its own HMIS form?
Yes. The Fire Prevention page links the Glendale Fire Department HMIS form, a spreadsheet listed as Regulation 5001.
Did Glendale change the hazardous materials rules locally?
The city’s 2024 fire code amendments do not amend Chapter 50, Section 5001.5.1 or Section 5001.5.2, so the International Fire Code text applies. The amendments do adopt Appendix H, used as the fire code official determines.
When is a management plan with a site plan required?
Under International Fire Code Section 5001.5.1, where the fire code official requires one with a permit application. The fire code official decides; ask before you order drawings.
Who do we ask at the city?
Glendale Development Services handles submittal questions at (623) 930-2800.
Does the state also want a site map?
If the facility files a Tier II report, yes. ADEQ states that a site map is mandatory with every Tier II report in its system, showing every way in and out, where substances are stored, and the general layout. Whether you must file is a question for ADEQ or your consultant.
Can one scan cover the Glendale drawing and the Tier II site map?
Yes. Both are drawn over the same measured floor plan, so one visit covers both. Your staff or your consultant supplies the chemical locations and hazard classes; we draw them in.
Sources, checked 28 November 2026: City of Glendale Fire Prevention page (code in force, Regulation 5001 HMIS form) and the Contractors Guide linked from it; City of Glendale 2024 fire code amendments and ordinance (City Code Chapter 16, Article II, as published for public notice); International Fire Code Section 5001.5.1; International Fire Code, 2024 edition, Appendix H (HMMP and HMIS instructions; the copy linked is the one the City of Tucson publishes); ADEQ Tier II Reporting page. The city’s code is the authority and it changes. RevealBuilt measures and draws. It is not a regulator and does not classify chemicals, prepare the HMIS or HMMP, or decide what you must file. For that, ask Glendale Fire Prevention through Development Services at (623) 930-2800.
Related
Tier II reporting and site maps, Arizona Tier II site map requirements, RevealBuilt in Glendale, and all compliance site maps and floor plans.
City guides: Gilbert, Mesa, Chandler, Phoenix, Scottsdale, Tempe, Peoria, Goodyear, Buckeye, Surprise, Queen Creek, Avondale.