Avondale’s certificate of occupancy floor plan, and the fire hazard questionnaire filed with it.

Moving a business into an existing Avondale building means a certificate of occupancy application, and the city wants a floor plan drawn to scale, a site plan and a fire hazard questionnaire with it. RevealBuilt measures the building and draws the plans.

What goes in with the application

Avondale’s certificate of occupancy packet lists five things:

  • The application, signed and dated
  • A consent to inspection form
  • The fire hazard questionnaire
  • A floor plan that is accurate, complete and drawn to scale
  • A site plan

The fire hazard questionnaire

The questionnaire asks, yes or no, whether the space will hold any of these:

  • Flammable or combustible liquids, aerosol products, compressed or liquefied gas cylinders
  • Liquid or solid oxidizers, organic peroxides, nitrate film or pyroxylin plastic
  • Other hazardous materials, battery rooms included
  • Hazardous material storage in any quantity
  • Spray booths, dust-producing operations, laboratories using chemicals, welding or cutting gas systems, commercial cooking
  • Combustible storage above 12 feet, or plastic and rubber products above 5 feet

The application asks you to explain any yes answer and list the materials used or stored with their quantities. The packet itself does not ask for an inventory statement or a management plan; the Fire and Medical Department reviews what you declare.

Who can draw the floor plan

  • A legible hand drawing is accepted only for a home or small building that is two stories or less, under 3,000 square feet, holds fewer than 20 people and is not changing occupancy.
  • A sealed drawing is required when the building is over two stories, over 3,000 square feet, holds more than 20 people or is changing use. The packet says a change of occupancy always needs a licensed registrant’s seal.
  • RevealBuilt does not seal drawings. We deliver the measured plan as DWG and PDF. For a small space that is the plan you file; for a larger one or a change of use, your architect or engineer works from our file and seals the result.

What the plans must show

The packet says the floor plan must show:

  • The outside walls of the entire building, with overall dimensions
  • Every interior room, hallway and storage closet, with dimensions for each
  • The planned use of each space, labeled
  • Doors and windows, with exits labeled
  • A north arrow and a scale
  • The prior use of the building or suite
  • Neighboring business types, in a connected building such as a strip center
  • Bathrooms, with accessible ones labeled
  • Accessible parking and the path to the entrance, if the site plan does not show them

The site plan shows a north arrow and scale (the packet suggests 1 inch to 20 feet), property lines and easements with dimensions, existing structures and setbacks, utility services, fences, the zoning district, the lot area and the allowable lot coverage.

Property lines, easements and setbacks come from a survey or the recorded plat, not from our scan. We measure the building and what stands on the site; we are not land surveyors.

Illustrative Tier II site map A fictional facility drawn the way a Tier II site map is laid out: the street and two gates, one building with a warehouse, production floor and office, four keyed chemical storage locations, an outdoor tank, utility shutoffs, the fire department connection, a hydrant, a north arrow and a legend. E EXAMPLE ROAD PROPERTY LINE GATE 1 (MAIN)GATE 2 (TRUCKS) OFFICEPRODUCTIONWAREHOUSE DOOR 1DOOR 2DOCKDOOR 3 ABCD EGW FH N LEGEND A Flammable liquids cabinet B Corrosives, drum storage C Battery charging area D Diesel tank, in containment E Electrical main G Gas shutoff W Water shutoff F Fire dept. connection H Hydrant Example Facility (fictional) 0000 E Example Rd Lat 33.0000, Long -111.0000 Drawn 2026-11-15 0 40 80 ft
Illustration only. On a phone, swipe the drawing sideways to see the legend. The facility, address and contents are made up. Your map shows your site, to scale, with the storage locations keyed to the chemicals on your own Tier II report.

How RevealBuilt fits

  • We scan the building once and draw a measured floor plan and site plan to scale, with north and the drawing date.
  • We place what the list calls for that we can see on site: exits, access, emergency equipment, tanks, shut-offs.
  • You or your consultant supply the chemical locations, hazard classes and control area boundaries, and we draw them in.
  • We do not classify materials, prepare the inventory statement or the management plan, or file anything with Avondale. We do not seal drawings or establish property lines.
What it costs

A measured as-built floor plan starts at $1,500 for a space up to 1,500 square feet and is priced by size from there, with DWG and PDF files and no travel charge anywhere in Avondale. A hazardous materials or Tier II site map from one scan is $500 plus $0.05 per square foot scanned.

Questions
Does Avondale require a floor plan for a certificate of occupancy?

Yes. The city’s certificate of occupancy packet lists a floor plan that is accurate, complete and drawn to scale, along with a site plan, the signed application, a consent to inspection form and the fire hazard questionnaire.

When does the floor plan need a professional seal?

The packet says professionally sealed drawings are required when the building has more than two stories, is over 3,000 square feet, holds more than 20 people or is changing use, and that any change of occupancy requires a licensed registrant’s seal. RevealBuilt does not seal drawings; your architect or engineer can work from our measured file.

What does the fire hazard questionnaire ask about hazardous materials?

Whether the space will hold flammable or combustible liquids, aerosols, gas cylinders, oxidizers, organic peroxides or other hazardous materials including battery rooms, and whether there will be hazardous material storage in any quantity. The application asks you to list the materials and quantities for any yes answer.

Does the Avondale packet ask for an HMIS or HMMP?

The certificate of occupancy packet does not mention either. Whether the Fire and Medical Department asks for one after reviewing your answers is its decision under the fire code.

How long is the application good for?

The packet says the application is valid for 180 days after the submittal date.

Does the state also want a site map?

If the facility files a Tier II report, yes. ADEQ states that a site map is mandatory with every Tier II report in its system, showing every way in and out, where substances are stored, and the general layout. Whether you must file is a question for ADEQ or your consultant.

Can one scan cover the Avondale drawing and the Tier II site map?

Yes. Both are drawn over the same measured floor plan, so one visit covers both. Your staff or your consultant supplies the chemical locations and hazard classes; we draw them in.

Sources, checked 28 November 2026: City of Avondale Development Services Certificate of Occupancy Application (revised 02.19.26; submittal list, floor plan and site plan requirements, Fire Hazard Questionnaire); ADEQ Tier II Reporting page. The city’s packet is the authority and it changes. RevealBuilt measures and draws. It does not seal drawings, survey property lines, classify materials or decide what you must file. For that, ask Avondale Development Services at (623) 333-4000.